Starting date (P and SCC)

The definition of "starting date" is set out in the CDM Glossary of Terms as follows:

The starting date of a CDM project activity is the earliest date at which either the implementation or construction or real action of a project activity begins (CDM Glossary of Terms, Version 03).

This definition was further discussed and clarified at EB 41:

"In light of the above definition, the start date shall be considered to be the date on which the project participant has committed to expenditures related to the implementation or related to the construction of the project activity. This, for example, can be the date on which contracts have been signed for equipment or construction/operation services required for the project activity. Minor pre-project expenses, e.g. the contracting of services /payment of fees for feasibility studies or preliminary surveys, should not be considered in the determination of the start date as they do not necessarily indicate the commencement of implementation of the project. For those project activities which do not require construction or significant pre-project implementation (e.g. light bulb replacement) the start date is to be considered the date when real action occurs. In the context of the above definition, pre-project planning is not considered “real action”.

The Board further noted that there may be circumstances in which an investment decision is taken and the project activity implementation is subsequently ceased. If such project activities are restarted due to consideration of the benefits of the CDM the cessation of project implementation must be demonstrated by means of credible evidence such as cancellation of contracts or revocation of government permits. Any investment analysis used to demonstrate additionality shall comply with the requirements of paragraph 7 of the "Guidance on the assessment of investment analysis" (EB 51, paragraph 67).

Related Topics

Crediting period (P)

Crediting period (SSC)

Project participants

Operational lifetime