How long does the Executive Board take to consider whether to register proposed project activities?

Once the DOE has submitted to the Executive Board a request for registration in the form of a validation report attaching the PDD, the Board initially has eight weeks in which to consider whether the project should be registered. At the conclusion of the eight week period, the registration is deemed final, unless a review is requested in accordance with the rules:

The registration by the Executive Board shall be deemed final eight weeks after the date of receipt by the Executive Board of the request for registration, unless a Party involved in the project activity or at least three members of the Executive Board request a review of the proposed CDM project activity (3/CMP.1, Annex, paragraph 41).